Newport Waterways – maintenance dredging
Project Communication Update
20739.105 – Newport – Waterways Canals
Maintenance Dredging
Project Details
Date of this update 24/02/2026
Project Number 20739.105
Project Title Newport – Waterways Canals – Maintenance Dredging
Status – In Construction
Percentage Complete – 40%
Commencement Date on Site – November 2025
Forecasted Completion Date on Site – April 2026
Working Hours – Monday – Saturday 7:00am – 6:00pm, excluding Public Holidays.
Works Completed This Period –
• Complete dredging at Kingfisher Canal (Zone 1, 2 and 3), between Southern Cross Dr and Australia Ct, Newport.
• Commence dredging at the Northern Marina, Newport.
Upcoming Works for Next Period
• Continue dredging at the Northern Marina, Newport.
Project Webpage
• Please refer to the Project Webpage for the above zone references
For more information
Council will endeavour to keep you updated on any changes to the above advice.
For further information please contact council:
• Phone: 07 3205 0555
• Email: council@moretonbay.qld.gov.au
• Website: Newport Waterways – Maintenance Dredging – City of Moreton Bay