Project Notice – Maintenance Dredging – UPDATE

Commence November 2025
Forecast completion April 2026

LINK TO CMB WEBSITE

NEWPORT DREDGING NEWS

LINK TO DREDGING UPDATE

Newport Waterways – maintenance dredging

Project Communication Update
20739.105 – Newport – Waterways Canals
Maintenance Dredging

Project Details
Date of this update 24/02/2026
Project Number 20739.105
Project Title Newport – Waterways Canals – Maintenance Dredging
Status – In Construction
Percentage Complete – 40%
Commencement Date on Site – November 2025
Forecasted Completion Date on Site – April 2026

Working Hours – Monday – Saturday 7:00am – 6:00pm, excluding Public Holidays.

Works Completed This Period –
• Complete dredging at Kingfisher Canal (Zone 1, 2 and 3), between Southern Cross Dr and Australia Ct, Newport.
• Commence dredging at the Northern Marina, Newport.

Upcoming Works for Next Period
• Continue dredging at the Northern Marina, Newport.

Project Webpage
• Please refer to the Project Webpage for the above zone references

For more information

Council will endeavour to keep you updated on any changes to the above advice.